Project Support Services Asia and Habib Rafiq (Pvt.) Limited have signed a MOU and formed a joint venture on the 2nd of April 2010, the two companies will be worki
PSS Asia has been awarded the total Turnaround Management of Major Shutdown Maintenance for BFPL’s Ammonia Plant in Karratha, WA.. The Shutdown was scheduled to begin on 1 July 2008 and resume Plant production on 17July 2008. Operations reserved handover to maintenance of the facilities from 3 July 2008 and to Turnover back on 15 July 2008. PSS Asia had its schedule for Pre-Turnaround mobilization of Cribs & Office facilities by 15 June 2008 and Supervisors and Pre-Turnaround crew by 20 June 2008. Scaffolding work was planned to start from 1 June 2008.